Team order planning

How to Plan a Team Uniform Order Backwards From the First Game

A team uniform order has one fixed date: the first game. Every other deadline comes from counting back from it. This guide lists the stages to count, shows how to build the schedule, and covers where late kits usually start.

By Maswiz Industries · 6 min read · Updated October 2026

Yellow soccer jersey with navy vertical stripes and navy shorts, ART# MI-2002 by Maswiz Industries
Key takeaways
  • Start from the first game and subtract every stage, including shipping and a spare buffer.
  • Artwork, rosters and size lists sit on the buyer's side, and they cause most delays.
  • Get production, sample and shipping times in writing before you fix a date.
  • Ask for kits to arrive well before the game so there is room for a fitting or a fix.

Why Counting Backwards Works

Most clubs plan forward: choose a design, place the order, and hope the kits arrive in time. The only date everyone remembers is the first game, so the schedule gets squeezed at the start, where the slow decisions are made.

Counting backwards flips that. You write down the game date, subtract each stage in reverse, and see the real latest day to start. Often it is earlier than expected. Better to learn that in week one than in the week of the game.

The Stages You Need to Count

A custom team order has more stages than the production run alone. Each one takes time, and some of them are controlled by you or your league rather than by the factory.

StageWhat happensWho controls the time
Design decisionsStyle, colors, sponsor logos, league kit rulesClub or team
Artwork and rosterFinal logo files, player names and numbersClub or team
Quote and sampleQuotation, sample made, sample approvedShared
Size collectionTry-on session, size list per playerClub or team
ProductionBulk run after approvalsManufacturer
Shipping and customsFreight, import clearance, local deliveryFreight forwarder
Handout and bufferFitting, fixes, spare daysClub or team

Three of the seven rows are entirely in your hands. That is useful: you can speed those up without asking anyone else.

How to Build the Schedule

  1. Fix the end point.Write down the first game date. Then choose the date you want kits in hand, ideally a week or more earlier so there is time for a fitting and for fixing a mistake.
  2. Get stage times in writing.Ask your supplier for production time, sample time and shipping time. At Maswiz, minimum order, lead time and sample terms are confirmed in the quotation, so use those figures rather than a guess. Our quote guide lists what to send to get an accurate one.
  3. Subtract shipping.Count back from the kits-in-hand date by the transit time. For duties, customs and delivery rules, confirm the details with your freight forwarder.
  4. Subtract production and sampling.Bulk production should start only after the sample, artwork, roster and sizes are all approved. Count back again by those stages.
  5. Set your own deadlines.Give the club a date for the final roster, a date for sizes, and a date for sign-off on the design. Then add a buffer of a few days to each handoff.

A Worked Example With Placeholder Numbers

The numbers below are placeholders to show the method. They are not Maswiz timings. Replace them with the figures in your own quotation.

Say the first game is in week 0. You want kits in hand at week minus 2. If shipping and customs take two weeks, goods must leave the factory by week minus 4. If production takes four weeks, it must start by week minus 8. If the sample needs two weeks to make and one week to review, approval must happen by week minus 11 and the sample request goes in earlier than that. Add a week for final artwork and roster, and design decisions land at about week minus 14.

Fourteen weeks before the first game feels early, but each step above is a real task. Cut the buffer and the schedule has no room for a color correction, a late roster change or a customs hold.

Tip: Make one person responsible for the schedule. Orders slip when the coach thinks the manager has the roster and the manager thinks the coach does.

What to Collect Before You Order

Most delays in the stages you control come from missing information. Gather these items before you ask for a quote, and the sample stage moves faster.

  • Logo and sponsor files in a format the factory can print from.
  • Color references. Our team kit color matching guide explains how to brief them.
  • A roster with names spelled correctly, and numbers with no duplicates.
  • A size list per player, taken at a try-on session. The sizing and fit guide shows how to measure.
  • League or tournament rules on colors, numbers and sponsor placement.
  • The delivery address and the date kits must arrive.

Pick the Style Early

The style affects sampling, so settle it first. For soccer, Soccer Uniforms ART# MI-2002 is a yellow jersey with navy vertical stripes, paired with navy shorts. For basketball, Basketball Uniforms ART# MI-9002 is a royal blue jersey and shorts with lime green side panels and trim. For baseball, Baseball & Softball Uniform ART# MI-8005 is a royal blue button-front jersey with yellow lettering and white pants.

All three are made in Sialkot, Pakistan, with custom colors, logos and sublimation printing available. If you are working on a soccer kit, the guide to designing a kit with names and numbers covers the layout choices that should be settled before the order.

Common Planning Mistakes

Starting from the order date

Planning forward hides how many weeks the later stages need. Start from the game and count back.

Ordering with an unfinished roster

Names and numbers change late. Settle them first, and ask how later additions are handled in the quotation.

Skipping the sample

An unseen color or fit problem found after the bulk run is far more expensive than a week spent on approval.

Forgetting the last mile

Customs, local delivery and handout take time. Confirm them with your freight forwarder.

Frequently asked questions

How far ahead of the first game should I order?

It depends on the stage times in your quotation, plus your own approval time and a buffer. Count back from the game date, as in the worked example above, rather than relying on a fixed number of weeks.

Can I order before the roster is final?

You can start design and sampling, but names, numbers and sizes need to be final before bulk production. Ask in your quote request how late changes are handled.

What are Maswiz's minimum order and lead time?

Minimum order, lead time and sample terms are confirmed in the quotation, since they depend on the product, quantity and decoration.

Who handles duties and customs?

Rules differ by country and by shipping terms. Confirm duties and import requirements with your freight forwarder before you set the delivery date.